The New York City Housing Authority is racing the clock to fix peeling and possibly lead-tainted paint in more than 2,800 apartments with young children to meet its commitment to a federal judge, The Post has learned.
The embattled agency first reported the tally in the second-to-last paragraph of court papers filed with federal Judge William Pauley late on a Friday, in which it promised to complete the work by the end of February.
The filing also revealed that only 190 of the potentially 2,862 lead-tainted units with kids had been remediated by the Dec. 11 court filing date, leaving a backlog of 2,672 apartments.
To meet its own deadline, the agency would have to make repairs in some 49 apartments every workday between Dec. 11 and Feb. 28.
Critics are skeptical NYCHA can meet that critical target for a judge who has criticized its operations and who has the power to put the city’s entire public housing system under federal receivership.
“They’ve been doing it for months. They’ve gotten 190 done,” said Elie Hecht, who reps NYCHA’s Citywide Council of Presidents tenant organization. “At the rate they’re going, they’ll be lucky if it’s February 2020.”
The agency insisted it is on track to meet the ambitious goal — but refused to provide data that could corroborate its claim.
“As of this Friday, we have attempted 100 percent of apartments that require inspections, showing our aggressive effort to meet our mandated deadline,” agency spokeswoman Jasmine Blake said last week.
But NYCHA wouldn’t say when it began cleaning up the first 190 apartments. Instead, officials told The Post to file a Freedom of Information Law request, a process that can take months.
The agency also said it has notified affected residents — without providing a time frame or details.
In the court filing, NYCHA said it mailed 165,000 lead disclosure letters to tenants, including 3,278 copies to households with children under 6 living in apartments believed to have lead paint.
Federal regulations require NYCHA to visually inspect 48,618 apartments in buildings where lead paint has been previously found, accounting for more than a quarter of the authority’s 176,000 apartments.
As of last week, NYCHA said, it had inspected and found paint issues in more than 34,000 of the apartments. All must eventually be fixed, but NYCHA said it prioritized the 2,862 units with young kids.
The sprawling housing agency has been rocked by a succession of scandals in recent months.
Perhaps the most egregious offense was when NYCHA’s then-chair, Shola Olatoye, falsely certified to the US Department of Housing and Urban Development in 2016 that the agency was in compliance with all lead paint inspections when it was not.
The coverup first exploded into public view in November 2017, when the city Department of Investigation exposed the scandalous behavior.
Then, this past August, Health Department officials revealed that 1,160 children who lived in NYCHA housing had tested positive for levels of lead that the federal government considers dangerous — although the source of contamination in many cases remains unclear.
Federal prosecutors in Manhattan sued NYCHA over the lead lies and scandalous living conditions last summer, which put the authority in Pauley’s hands and set the stage for a possible federal takeover of the agency.
The city has until Jan. 31 to strike a deal with federal prosecutors and HUD on a rescue plan to present to the judge.